Rough / general guidelines are shown below, for someone whom:
Summary: possibly 2 to 4 months
Details:
Initial Preparation - 1 to 2 weeks
Determine basic Zoning Requirements
On-site Consultation
Decision to go-ahead
Discovery Stage - 1 to 4 weeks
Identify Legal Restrictions
Site Review
On-site Measurements (if req'd)
Design Questionnaire
Property & Topo Survey (if req'd)
Design Phase - 3 to 5 weeks
Preliminary Design
Design Development
Construction Drawing Phase - 3 to 5 weeks
Architectural Drawings
Structural Drawings
Summary: possibly 4 to 6 months
Details:
Initial Preparation - 1 to 3 weeks
Determine basic Zoning Requirements
On-site Consultation
Decision to go-ahead
Discovery Stage - 2 to 4 weeks
Identify Legal Restrictions
Site Review
On-site Measurements (if req'd)
Design Questionnaire
Property & Topo Survey (if req'd)
Design Phase - 1.5 to 2 months
Preliminary Design
Design Development
Construction Drawing Phase - 1.5 to 2 months
Architectural Drawings
Structural Drawings
Summary: possibly 6 to 8 months
Details:
Initial Preparation - 2 to 4 weeks
Determine basic Zoning Requirements
On-site Consultation
Decision to go-ahead
Discovery Stage - 2 to 5 weeks
Identify Legal Restrictions
Site Review
On-site Measurements (if req'd)
Design Questionnaire
Property & Topo Survey (if req'd)
Design Phase - 2 to 3 months
Preliminary Design
Design Development
Construction Drawing Phase - 2 to 3 months
Architectural Drawings
Structural Drawings
Summary: possibly 6 to 8 months
Details:
Initial Preparation - 2 to 4 weeks
Determine basic Zoning Requirements
On-site Consultation
Decision to go-ahead
Discovery Stage - 2 to 5 weeks
Identify Legal Restrictions
Site Review
On-site Measurements (if req'd)
Design Questionnaire
Property & Topo Survey (if req'd)
Design Phase - 2 to 3 months
Preliminary Design
Design Development
Construction Drawing Phase - 2 to 3 months
Architectural Drawings
Structural Drawings